pplo5956 pplo5956 Today at 1:28 AM Business Answered Given the following data, which job(s) will be late if the shortest process time sequencing rule is used?Today is day 100.Job Process DueTime DateA 4 104B 1 106C 5 109a) all jobs will be on timeb) A and B will be latec) A and C will be lated) B and C will be late